Mandan, North Dakota Fence
Project Name
Project Description
SCOPE OF WORK
- Site excavation and leveling
- Post-frame structural engineering
- Steel siding and roofing installation
- Underground utility integration
- Interior framing and insulation
PROJECT TIMELINE
- Phase 1: Planning & Design (2 Weeks)
- Phase 2: Foundation & Dirt Work (3 Weeks)
- Phase 3: Structural Construction (8 Weeks)
- Phase 4: Finishing & Utilities (4 Weeks)
- Completion: 17 Weeks Total
KEY FEATURES
- High-durability precision framing
- Energy-efficient thermal barrier
- Customized interior floor plan
- Industrial-grade steel skin
- Integrated septic management